1603473979831_photo17.jpgThe construction of Hemus Motorway in the section between Boaza and the connection to Pleven - Lovech road is progressing. Currently excavations and embankments are being carried out on the route, divided into three sections, work on the major facilities is being proceeded - bridges, viaducts, road junctions, subways and overpasses.


 


In the execution of the construction works the company Avtomagistrali EAD has mobilized 69 chain, 23 combined and 7 wheeled excavators, 33 bulldozers, 14 cement trucks, 5 concrete pumps, 31 rollers, 13 tugs, 6 graders, 18 water carriers, 11 dumpers, 2 tower cranes, 12 cranes, 2 trucks with a crane, 3 telescopic loaders, 21 loaders, 3 crushers, 257 dumpers, 2 recyclers, 5 pilot machines. The work on the site is fully mobilized.

The gradual construction of the route between Boaza and the connection to Pleven - Lovech road is divided into 3 sections. The 51.5 km stretch will have 17 viaducts, 5 bridges, 5 junctions, 9 overpasses and subways and one tunnel.

Section 1, with a length of 15.26 km, starts from Boaza and it will be until the crossing with Lukovit-Ugarchin road, including “Dermantsi” road junction. It is envisaged to have two road junctions, four bridge facilities and 2 viaducts. Construction works are carried out in three subdivisions. In the first one it is about 25.5%, in the second one – about 59.5%, and in the third one – about 2%.

Section 2 begins at the end of the road junction “Dermantsi” and it is next to the connection with the road III-3005 Radyuvene-Katunets, including road junction “Kalenik”. Its length is 19.2 km and there will be 2 road junctions in it, 9 viaducts, a bridge over the river Kamenitsa and a tunnel with two separate pipes. Activities are being carried out in connection with the opening of the construction site.

In Section 3, with a length of 17.08 km, there will be one road junction – “Pleven” which will be at the end of this stretch, which will reach the connection with the road Pleven – Lovech. It will have 6 viaducts and nine overpasses and underpasses. Approximately 7.5% out of the planned construction and installation works on this route have been completed.

The complete construction of Hemus Motorway by 2024 is a major priority in the Program of the Government, as the future of Northern Bulgaria and the modernization of the region is related to the construction of the motorway and ensuring fast and safe road communication between Sofia and Varna. Currently the sections from Sofia to Boaza and from the village of Belokopitovo to Varna, with a total length of about 180 km, are put into service. The unfinished part, from the road junction Boaza to the village of Belokopitovo will connect these already built sections on both sides of the motorway.

The company Avtomagistrali EAD is entrusted with the design and construction of 223.04 km from Hemus Motorway in the sections from Boaza road junction to the intersection with road I-5 Ruse - Veliko Tarnovo /134.14 km/ and from the connection with the road Ruse - Veliko Tarnovo to Belokopitovo /88.9 km/. For the segment from the connection with the road Pleven - Lovech to the intersection with road I-5 /sections 4, 5 and 6/ the technical projects are worked out, Detailed Development Plan - a plot plan is being proceeded, which are at the approval stage. For the route after the connection with the road Ruse - Veliko Tarnovo /sections 7, 8 and 9/ work regarding the route design is currently being proceeded.

 